Energy Commissioning on Commercial Construction

The International Energy Conservation Code has require a commissioning report for a few code cycles.

This report is required to be presented prior to or at the time of final inspection of the building. This is not a differed report, and is required to address the following:

  1. Itemization of deficiencies found during testing required by this section that have not been corrected at the time of report preparation.

  2. Deferred tests that cannot be performed at the time of report preparation because of climatic conditions.

  3. Climatic conditions required for performance of the deferred tests.

  4. Results of functional performance tests.

  5. Functional performance test procedures used during the commissioning process, including measurable criteria for test acceptance.

Please see a blank template (fillable PDF).